BLOCKWALL MASONRY 18 INC
Field Manager · Daily Report
Report Date
Sep 23, 2026
Report No
FMDR-2026-09-23
From
Field Manager · Site
To
Blockwall Office / Project file
Project
North Dumfries Community Complex — Arena Addition (Ayr, ON)
Task
Masonry — field daily
Title
Field Manager Daily Report
What this is. Blockwall’s daily field record for the North Dumfries Arena Addition. It covers weather, delays, work areas, labour, production by floor and wall, deliveries, equipment, safety, inspections, photos, and the official document / query log — ready for schedule talks and, if needed later, discussions with the GC and consultants.
Weather today: dryNo weather stop2 queries waitingRFI #16 P4 veneer openSample day — review yellow notes
Dry
Weather today
2
Waiting on answers
3
Docs this week
Open
Need confirm · delays

How the day went

Built
ProductionWalls and block counts still blank on this sample. Use §5 once the Field Manager locks today’s numbers.
Crew
People on siteEmployee and subcontractor headcount by role goes in §4 (labourers, bricklayers, operator, foreman).
Blocked
What held us upNo project delays confirmed yet. Today was dry. Still open: door swing in Rm 253, and CMU height at door E22.
Next
Ready tomorrowField Manager lists unlocked areas first thing tomorrow.
Decide
Open decisionsQ-01 Rm 253 frames · Q-02 CMU height at E22 · RFI #16 P4 veneer product still unclear.
Blocks today
Blocks / hour
Men today
Days ahead / behind
Open areas of work
1+
Areas blocked
3
New docs this week
2
Waiting on answers
Need equipment
Need materials

SAMPLE — numbers marked “—” and yellow notes need Field Manager review before this report is issued.

1 Weather — conditions & delays
0 mm
Rain today
8–19°C
Low / high
30 km/h
Wind peak
No stop
Weather delay
Today’s conditions
Sky
Overcast (dry all day)
Temperature
Low 8.4 °C · High 18.9 °C
Wind
Max 29.6 km/h · strongest mid-afternoon
Morning (7:00)
9.2 °C · clear · wind 15 km/h · no rain
Midday (12:00)
17.9 °C · clear · wind 27 km/h · no rain
Afternoon (15:00)
18.5 °C · clear · wind 30 km/h · no rain
Precipitation
0.0 mm · 0 rain hours
Workability
Good for masonry — dry; breezy afternoon
Weather delays (last 3 weeks)

Hours lost need Field Manager confirmation before any claim or GC discussion.

Delay NoDateHours lostConditionsStatus
W-012026-09-02Confirm with Field ManagerLight drizzle · wind up to 47 km/hReview
W-022026-09-03Confirm with Field ManagerDense drizzle · 1.1 mmReview
W-032026-09-09Confirm with Field ManagerLight rain · 3.3 mm · 3 rain hoursReview
W-042026-09-19Confirm with Field ManagerLight drizzle · 0.4 mmReview

Weather source: Open-Meteo · Ayr / North Dumfries · Sep 2–23, 2026

2 Project delays & impacts
0
Confirmed delays
3
Suggested · pending
Hit tomorrow
Hit this week
Confirmed delays

Nothing confirmed on this sample. Suggestions below are examples only — do not use them until the Field Manager approves.

Delay NoSinceDescriptionAffects tomorrowAffects this weekStatus
None confirmed on the sample date.Empty
Suggested examples — waiting for Field Manager approval
SuggestTopicWhy it may matterStatus
S-01Door swing Rm 253 — reverse framesNotes from Sep 22–23 — may stop masonry at the doorPending
S-02CMU height under door E22Follow-up after masonry RFI-01Pending
S-03P4 veneer product (RFI #16)Manufacturer still unclear — may delay orderingPending
Affecting tomorrow (confirmed only)
Delay NoAreaImpact
Affecting this week (confirmed only)
Delay NoAreaImpact
3 Work areas & narrative

Example wording — Field Manager rewrites from site.

Ready: NM1 East (example)Detailing: lintels / MJsAction: Rm 253 frames
Areas ready to work
Ground floor / East — parts of NM1 load-bearing (example — review)
Areas worked today
— (fill from site)
Sequence / method
Detailing
Openings, lintels, and movement joints per CCO #08 and #09 — check on site (example — review)
Finished today
In progress / carry-over
Blockwall action needed
Lock the Rm 253 frame decision before more work at that door (example — review)
Supervisor notes
4 Labour
Employees
Subcontractors
Bricklayers
Total men
Employees
RoleHeadcountHoursStartFinishNames / notes
Labourers
Bricklayers
Operator
Foreman
Subcontractors
RoleHeadcountHoursStartFinishNames / notes
Labourers
Bricklayers
Operator
Foreman
Others
5 Production & schedule
Blocks today
Blocks / hour
Balance left
Days ahead / behind

The row below shows the format only.

Level / zoneWall / areaBlocks todayHoursBlocks/hrCount methodPhotoNotes
2nd floor / East (example)Partition walls / N16–N18 / NP–EN (example)Photo / field countY/NReview with Field Manager
Job total (locked)
______
Cumulative to date
______
Balance
______
Days left at this pace
______
6 Materials — site deliveries
Deliveries today
Need materials
Short / back-order
Office order qty

Delivery lines wait on Blockwall supplier emails and tickets.

Delivery dateMaterialSupplierTicket / BOLQty deliveredUnitOffice order qtyLocation on siteStatusNotes
CMU / mortar / grout / rebar / tiesWaiting on ticketsExample row
7 Equipment
Units on site
Need equipment
Down / repair
Hours meter
EquipmentOwnerDelivered onOn-site durationHours meterStatusInfo
Scaffold / accessBlockwallFrom delivery log or verbal daily
Mortar mixerBlockwall
Masonry sawBlockwall
Telehandler / forklift
Chipping gunBlockwallNoted in earlier progress (example — review)
8 Safety logs
JSAHeavy equipmentTools checkSafety talk
JSA
DateTimeArea / taskByResultStatusNotes
Heavy equipment check
DateTimeArea / taskByResultStatusNotes
Tools / equipment check
DateTimeArea / taskByResultStatusNotes
Site inspection / safety talk
DateTimeArea / taskByResultStatusNotes
9 Visitors & inspections
CityEngineerArchitectGC3rd party
City inspection
DateTimePerson / companyPurposeResultStatusNotes
Engineer consultant
DateTimePerson / companyPurposeResultStatusNotes
Architect consultant
DateTimePerson / companyPurposeResultStatusNotes
GC
DateTimePerson / companyPurposeResultStatusNotes
3rd party
DateTimePerson / companyPurposeResultStatusNotes
10 Evidence — pictures needed

Photo list matches only the sections in this report.

Progress shots neededDelivery shots on arrivalSafety / inspection if it happens
From §1 Weather
Shot neededStatus
Site conditions if a weather delay (W-##) is claimedIf delay confirmed
From §2 Delays
Shot neededStatus
Blocked area named on a confirmed delayIf delay confirmed
From §3 Work / detailing
Shot neededStatus
Ready-to-work overviewNeeded
Work in progressNeeded
Detailing / special conditionsAs needed
From §5 Production
Shot neededStatus
Each level / zone and wall area countedNeeded
Block-count proof (wide + close-up)Needed
From §6 Materials
Shot neededStatus
Delivery ticket / BOLOn delivery
Material stacked with quantity visibleOn delivery
From §7 Equipment
Shot neededStatus
Unit on site and hours meter if shownAs needed
From §8 Safety
Shot neededStatus
Signed JSAAs needed
Heavy equipment check / tagAs needed
Tools checkAs needed
Safety talk attendanceAs needed
From §9 Inspections
Shot neededStatus
Inspector or visitor on siteIf visit
Result or deficiency tagIf visit
11 Document Log — official & team queries
11
IFC · CCO · SI
5
Official RFIs
2
Team queries open
1
RFI waiting (#16)

Official consultant / GC documents only. Internal models, obsolete PDFs, shop drawings, and surveys stay off this log.

A) IFC · CCO · SI (official)
TypeDocumentRevDoc dateOn fileStatusSummary for masonrySource
IFCNDCC Drawings — Issued for ConstructionIFC2026-09-21On fileCurrentMain IFC architecture and structural set.Official
IFC / detailsD4 — Masonry2026-09-10On fileCurrentMasonry detail package.Official
CCOCCO #04 — Reinforced non-loadbearing masonry (MML)2026-09-08On fileCurrentWall type, movement joints, and pier clarifications.Official
CCOCCO #04 (site instructions copy)2026-09-16On fileCurrentMatching CCO #04 in the site instructions set.Official
CCOCCO #07 — Non-loadbearing block wall specs2026-09-16On fileCurrentNon-loadbearing block specification changes.Official
CCOCCO #08 — Transition area revisions2026-09-14 / 09-21On fileCurrentTransition joints, openings, MP2, lintel L3.Official
CCOCCO #09 — Missing lintels2026-09-16On fileCurrentEO opening N14–N15 lintels; Zamboni overhead door courses.Official
CCOCCO #13 — Wall change for sanitary piping2026-09-16On fileCurrent4" CMU chase in front of loadbearing wall, rooms 254/255.Official
CCOCCO #15 — Roof revisions2026-09-16On fileReviewEXAMPLE — confirm masonry impact with Field Manager before citing.Official · review
CCOCCO #17 — Workshop wall removal / ERV2026-09-16On fileReviewEXAMPLE — confirm masonry scope with Field Manager before citing.Official · review
SISI-02 (2026-04-10)2026-04-10On fileCurrentMP2 piers at N22 louvres; footing and pier top notes.Official
B) RFI (official)
TypeDocumentRevDoc dateStatusStateSummary for masonrySource
RFIRFI #16 — P4 wallOn file 2026-09-16WaitingWaiting90 mm P4 veneer — name, size, manufacturer still unclear.Official
RFIRFI #31 — Block movement joints (answered 2026-06-25)2026-06-25AnsweredAnsweredMovement values for about 6 m joint spacing.Official
RFIRFI #35 — Rainwater leader chaseOn file 2026-09-16AnsweredAnsweredChase size vs 8" RWL in rooms 155A/154.Official
RFIRFI #36 — Sanitary pipe in loadbearing wallOn file 2026-09-16Answered → CCO #13AnsweredResolved by chase — see CCO #13.Official
RFIRFI-01 — Doors D258A/B (answered 2026-09-18)2026-09-18AnsweredAnsweredTeam RFI: 400 mm from EO inside face for MP4.Official (team-issued)
C) Queries from our team only
NoTopicDateStatusSummaryNote
Q-01Door swing Rm 253 — reverse two frames2026-09-22 → 09-23OpenArchitect / code direction to reverse frames. Bolt carefully to avoid a back-charge.Team query
Q-02CMU height under door E22 / NM1–EL2026-09-18Follow-upFollow-up after RFI-01 — height of block under the door.Team query